Ladue's New Crosswalk Is a Down Payment on a Trail That Isn't Finished Yet

September 10, 2026

Anyone who drives Clayton Road past Sportsman's Park this month has probably noticed the new pole and signal box planted at the crosswalk out front. It looks like nothing much. A pedestrian HAWK signal, the kind that stays dark until someone pushes a button, then flashes to stop traffic long enough for a person on foot to cross. Ladue installed it at 9901 Clayton Road specifically so people leaving that bar, or heading to it, don't have to time a gap in traffic themselves.

What the signal does not explain, sitting there on its own, is why the city spent nearly $190,000 putting it in, or why it exists at all on a stretch of road that already has a stoplight less than a block away. The answer has almost nothing to do with this particular crosswalk. It has to do with a trail two years from being finished, a mulch pile that became a nature preserve, and a public works department that has been laying track for this exact connection since before most residents noticed anything was happening.

The Signal Cost More Because of a Finial

City records show Ladue's Public Works department awarded the signal contract to Gerstner Electric for $188,633.20, approved by the city council in March through Resolution 2026-07. Gerstner was the lowest of three bidders. That number matters against what it replaced: the project's original budget line was $137,000, and even a February consultant estimate that bumped the figure to $198,000 still landed under what the final contract required.

The overrun didn't come from wiring or poles. City documents attribute it to "custom aesthetic requirements, including a decorative finial designed to match the pedestrian signals already installed nearby." In other words, Ladue paid extra to make sure a traffic signal matches the ironwork on the ones already standing down the street. The city covered the gap using roughly $200,000 in savings it had banked from a separate microsurfacing project, so the work went forward on schedule rather than waiting for another budget cycle.

That single decision says something about how this city builds things. It is not in a hurry, and it will not tolerate a mismatched pole on Clayton Road, even for a signal most drivers will pass a thousand times without a second look.

The Sidewalk Work Was Already Years Deep

The Sportsman's Park signal is not a standalone idea. It traces back to a 2022 pedestrian walkability audit that engineering firm CBB conducted along the Clayton Road business corridor, checking unprotected crosswalks for exactly the kind of gap this signal now closes. That audit fed into a citywide Walk Plan the city council adopted in April 2023, based on a study from Horner and Shifrin, the same firm now handling the trail work described below.

Clayton Road's sidewalks themselves have been under construction in phases for most of the past decade. Phase I, covering the business district between I-64 and Conway Road, wrapped in summer 2019. Phase II, from Warson to Eversdale, finished in spring 2020. Phase III, Eversdale to Lindbergh, was done by spring 2021. A signal outside a specific bar looks like a small, almost decorative gesture until you see it as the latest link in a chain that has been assembled one segment at a time since before the pandemic.

Where the Path Is Actually Headed

The reason this particular crosswalk matters more than it looks is what the city says it is designed to connect to. Planning documents describe the new signal as built to eventually link with a shared-use path planned for 2027 along South 40 Drive, one that would run the Deer Creek Preserve trail directly into the Clayton Road business district. Horner and Shifrin, the firm behind the 2023 Walk Plan, was awarded the design contract for that path extension back in October 2024.

Deer Creek Preserve itself has a longer and stranger backstory than its current quiet green space suggests. The 14 acre parcel, purchased from Ameren in 1988, spent decades as the city's mulch processing site, informally known as Edie's Mulch Site after Mayor Edie Spink, who served from 1975 to 1995. The program was discontinued in 2017 once the city calculated that only about 11 percent of residents were actually participating, against rising costs to keep it running.

What came next is a genuinely local effort. Starting in 2019, the Ladue Garden Club and the Garden Club of St. Louis partnered with the city's Beautification, Open Space and Tree Advisory Committee to turn roughly 11 of those 14 acres into a walking and biking preserve. Phase I, a trail system, a bridge over the creek, benches, and native tree plantings, was finished in time for a ribbon cutting on Arbor Day, April 27, 2024. The city is now surveying residents about a Phase 2 looped trail and scenic overlook along the creek, with an eye toward a Municipal Park Grant application this year.

So the sequence runs like this: a walkability audit becomes a citywide plan, the plan produces a mulch site turned preserve, the preserve gets a trail nobody can reach without a car, and the path meant to connect it to the business district on foot is still two construction seasons away. The signal outside Sportsman's Park is the first piece of hardware in that last, missing link. It works today for someone crossing to get a drink. It is built for a walk that does not fully exist yet.

The Storefronts Move Faster Than the Sidewalks

Set against that multi-year infrastructure timeline, the retail side of the corridor turns over in a fraction of the time. The storefront at 8853-Q Ladue Road has cycled through three concepts in roughly the same window it took to plan one crosswalk. MaggieMoo's occupied the space first. JARS by Fabio Viviani opened there in August 2024 to a crowd waiting for the celebrity chef's jar-based desserts, then closed earlier this year after a 19-month run. This past August, Playa Bowls moved in, its first Missouri location, part of a five-unit development deal a St. Louis cardiologist and his wife signed to bring the fruit bowl chain into the metro area.

A few doors down, Companion Ladue keeps running its own quieter rhythm on Clayton Road, with Ladue Taco tucked into the alley behind it serving tacos only in the evenings. Those two spots barely change year to year, which is part of what makes the corridor work. Some tenants rotate in eighteen months. Others have been fixtures long enough that regulars stopped noticing them as new.

The One Piece Still Off the Map

Not everything green in Ladue is headed toward a public trail. The Litzsinger Road Ecology Center, a roughly 39 acre study site on Litzsinger Road managed by the Missouri Botanical Garden, sits close to this same stretch of the city but isn't part of any current walk plan. It holds bottomland forest, a restored prairie, and an urban creek, and it exists almost entirely for place-based science education, hosting field trips for area schools. It is not open to the general public, and a visit requires an appointment. Whatever comes of the South 40 Drive path or Deer Creek Preserve's next phase, this particular 39 acres stays exactly as accessible as it has always been, which is to say, not very.

That contrast is worth sitting with. Ladue has spent years and real money making sure one crosswalk matches its neighbors and one mulch pile became a preserve with a name and a ribbon cutting. Meanwhile a much larger tract of restored habitat sits a few blocks away, doing exactly what it was built to do, for exactly the audience it was built for, with no plan to open it further.

The next time you pass that new signal outside Sportsman's Park, it's worth knowing what it's actually pointing toward. Not a finished walk, not yet. A promise the city has been paying installments on since 2019, with the last big payment due sometime in 2027.

If you're watching how a specific corner of Ladue changes, or you're thinking about what a move within West County might look like once you understand a neighborhood at this level of detail, Sandra Mesker has spent her career paying attention to exactly this kind of local detail. Schedule a private consultation when you're ready to talk.